Accepted Answer
The crucial scrum artifact that has the function of graphically displaying progress on every sprint during the monitoring and controlling process is called a burndown chart.The product increment is always thought of as the most important of the three artifacts of Scrum. It's the kind of the product that will be transfer at the end of each sprint. Whereas, the sprint backlog outlines what must be fulfilled within a sprint, the product increment details the outcome of all that work. A burndown chart present the amount of work that has been fulfilled in an epic or sprint, and the total work remaining. Burndown chart is used for speculating your team's likelihood of completing their work in the time available.Learn more about The scrum artifact at https://brainly.com/question/29062642#SPJ4