Ten men working 6 hours a day takes 12 days to complete a job.How long will it take 8 men working 12 hours a day to complete the same job

See Answers (1)

Suggested Answer

Answer:It will take 7.5 days to complete the job. Step-by-step explanation:First, find how many total hours the ten men worked to complete the job10 x 6 = 60 hours a day 12 x 60 = 720 hours totalNow compare that with the 8 men's hours8 x 12 = 96 hours a day 720 / 96 = 7.5 days